Timeline​

Change Management, Communications and Roadmap Development​

Jan 2026​

Prepare Phase

Discovery sessions to identify vision, goals and high-level system requirements ​

Feb – May 2026​

Design and Deliver Phase ​

System Build “Sprints” to iteratively build the system to specifications ​

​June 2026​

Deploy Phase

  • Final Development, Enhancements and
    User Acceptance Testing (UAT)​
  • Training & Enablement for July launch.​

July – August 2026 ​

Go Live Phase

  • Campus-wide Rollout​
    • July 7: Launch People360 General Intake Form ​
    • Go Live Support​
  • ​Training & Enablement for launch​

​​September 2026​

Refine and Finalize

  • Target enablement & continuous improvement based on insights

October 2026 – onward​

Go Live and Adoption

  • Campus-wide Rollout
    • Launch Personnel Action
    • Go Live Support​ and Enablement
  • Institutionalization & Value Realization
  • Target enablement & continuous improvement based on insights