Timeline
Change Management, Communications and Roadmap Development

Jan 2026
Prepare Phase
Discovery sessions to identify vision, goals and high-level system requirements

Feb – May 2026
Design and Deliver Phase
System Build “Sprints” to iteratively build the system to specifications

June 2026
Deploy Phase
- Final Development, Enhancements and
User Acceptance Testing (UAT) - Training & Enablement for July launch.

July – August 2026
Go Live Phase
- Campus-wide Rollout
- July 7: Launch People360 General Intake Form
- Go Live Support
- Training & Enablement for launch

September 2026
Refine and Finalize
- Target enablement & continuous improvement based on insights

October 2026 – onward
Go Live and Adoption
- Campus-wide Rollout
- Launch Personnel Action
- Go Live Support and Enablement
- Institutionalization & Value Realization
- Target enablement & continuous improvement based on insights